Progress of the construction Made 2

  • Progress of the construction Made 2

So far the construction is progressing well, although it is always exciting until the last moment: Will everyone be ready on time and can we actually start to cultivate from week 44/45 at Made 2? It depends on a number of our construction partners. We would like to introduce them to you and inform you what they are doing during construction.

Voshol Warmte-Elektrotechniek
Appropriate temperature control is of paramount importance for our production. Currently the tubes for the heating system are running through the ground and a part is mounted on the facades. In addition to that, the floor heating should be ready so it can be extorted later, before the concrete goes on it. Only after the concrete is poured, the lift installation will be installed.

Boekestijn Elektrotech
Growing light in the greenhouse gives an increase in production and an improved quality. The lighting cables are running through the ground and the power supply, as well as the rails for armatures are suspended. The armatures themselves will be suspended when the concrete is poured. Boekestijn also mounted all cable ducts.

Screen4seasons
The installation of the display mechanism has reached an advanced stage. The actual screens will be mounted when the concrete floor has been poured.

BE
Pipes for watering are running mostly through the ground. This also applies for the pipes where the silos will be built on. These silos and the rain unit as well (as it now appears) will be built in week 41, right after the pouring of the concrete.